Question: show work Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of

show work
show work Using the information provided in the
show work Using the information provided in the
Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 5 weeks in the most economical way. Normal Time Normal Cost ($) Crash Time (weeks) Crash Cost ($) Maximum Weeks Reduced Crash Cost per Week ($) Activity (weeks) 3 500 2 880 1 380 B 4 650 3 750 1 100 c 6 6 750 3 1,230 3 160 D 6 1,400 4 2,020 2 310 E 6 6 1.750 4 2,230 2 240 F 5 200 5 0 200 0 G 7 1,400 5 150 1.700 2 H 0 3 450 3 450 AON network diagram B(4) E(6) A(3) C(6) G(7) H(3) D(6) F(5) If there is no amount for a box enter 0. All boxes must be filled.) Reduce A by week(s), B by week(s) C by I week(s), D by week(s). E by week(s). F by week(s), G by week(s). H by week(s). Total additional cost is $

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!