Question: Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project
Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 5 weeks in the most economical way.
| Activity | Normal Time (weeks) | Normal Cost ($) | Crash Time (weeks) | Crash Cost ($) | Maximum Weeks Reduced | Crash Cost per Week ($) |
|---|---|---|---|---|---|---|
| A | 3 | 500 | 2 | 900 | 1 | 400 |
| B | 4 | 650 | 3 | 740 | 1 | 90 |
| C | 6 | 850 | 3 | 1,345 | 3 | 165 |
| D | 6 | 1,500 | 4 | 2,180 | 2 | 340 |
| E | 6 | 1,900 | 4 | 2,420 | 2 | 260 |
| F | 5 | 200 | 5 | 200 | 0 | 0 |
| G | 7 | 1,450 | 5 | 1,750 | 2 | 150 |
| H | 3 | 500 | 3 | 500 | 0 | 0 |
AON network diagram 
(If there is no amount for a box enter 0. All boxes must be filled.) Reduce A by enter a number of weeks week(s), B by enter a number of weeks week(s), C by enter a number of weeks week(s), D by enter a number of weeks week(s), E by enter a number of weeks week(s), F by enter a number of weeks week(s), G by enter a number of weeks week(s), H by enter a number of weeks week(s). Total additional cost is $enter total additional cost in dollars .
A(3) B(4) D(6) C(6) E(6) F(5) G(7) H(3)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts