Question: Shown below is the project network diagram for a small Office renovation project. The numbers in the nodes are the activity times 0 % Suppose

Shown below is the project network diagram for a
Shown below is the project network diagram for a small Office renovation project. The numbers in the nodes are the activity times 0 % Suppose that activities B. C. and D can each be crashed by one week at a cost of $500 aplece. Activities A and E cannot be crashed. Which actiwny should be crashed in order to reduce the duration of the project by one week? Multiple Choice Since the cows are all the same, doesn't moner which one crushed Oceny B O activity O activity