Question: Shown below is the project network diagram for a small office renovation project. The numbers in the nodes are the activity times. A NM uo

Shown below is the project network diagram for a
Shown below is the project network diagram for a small office renovation project. The numbers in the nodes are the activity times. A NM uo What is the earliest start time for activity E? Multiple Choice 7 weeks 9 weeks 12 weeks 19 weeks