Question: Shown below is the project network diagram for a small office renovation project. The numbers in the nodes are the activity times. B 4 D

Shown below is the project network diagram for a

Shown below is the project network diagram for a small office renovation project. The numbers in the nodes are the activity times. B 4 D 3 A 2 E 2 10 Suppose that activities B, C, and D can each be crashed by one week at a cost of $500 apiece. Activities A and E cannot be crashed. Which activity should be crashed in order to reduce the duration of the project by one week