Question: simple CPM network has five activities, A , B , C , D , and E . A is an immediate predecessor of B and
simple CPM network has five activities, A B C D and E A is an immediate predecessor of B and of C B and C is immediate prodecessor of D D is immediate predecessors of E Which of the following statements is TRUE?"
There are four paths in this network
There are five paths in this network.
The critical path is ABDE
The duration of critical path is
The duration of critical path is