Question: Since activity G has a total float equal to zero (0), activity G is part of the critical path. True False In Backward Pass Algorithm,
Since activity G has a total float equal to zero (0), activity G is part of the critical path.
True
False
In Backward Pass Algorithm, ET(0) = 0.
True
False
Item at position 3
If the following times are estimated for an activity of the project, calculate the mean using PERT analysis.
a = 5
b = 13
m = 9
If the following times are estimated for an activity of the project, calculate the mean using PERT analysis.
a = 5
b = 13
m = 9
7
12
10
9
Item at position 4
If the following times are estimated for an activity of the project, calculate the variance using PERT analysis.
a = 5
b = 13
m = 9
0.4
1
1.78
2.78
5
PERT assumes that the durations of the activities are statistically dependent.
True
False