Question: since image is not clear: A 0.4 B 0.5 C 0.7 D 0.6 E 0.4 F 0.6 G 0.8 Task Time (Minutes) 04 c 02
since image is not clear:
A 0.4
B 0.5
C 0.7
D 0.6
E 0.4
F 0.6
G 0.8
Task Time (Minutes) 04 c 02 D E 3 Balance the following assembly line. Primary Heuristic assign sub-station with largest positional power / Tie-Breaker Heuristic: Assign sub-station with longest time Desired Outpu: 60 units per hour Operating Time: 60 units per hour a) What is the Cycle Time ? b) What is the minimum number of workstations? c) Which sub-stations will be grouped together in each station? d) What is the line efficiency? Revised Time Assign Time Station Remaining Workstation Remaining Eligible Task Idle Time 06 04 06 G 30 DISPLAY CALCULATIONS HERE