SITUATION A:
a. Construct a project network.
b. Determine the project completion time.
c. Calculate slack values of each activity.
d. What is the critical path?
\table[[Activity,A,B,C,D,E,F,G],[\table[[Immediate],[Predecessors]],,,A,A. B,D,C. E,E],[\table[[Expected],[Time],[(Weeks)]],12,12,17,12,5,12,15]]
Use this format ONLY
\table[[Activity,ES,EF],[Time (duration),LS,LF]]