Question: Six jobs must be processed through machine A and then B as shown below. The processing time for each job is also shown. Machine (minutes)

Six jobs must be processed through machine A and then B as shown below. The processing time for each job is also shown.

Machine (minutes)

JOB A B
1 10 6
2 6 12
3 7 7
4 8 4
5 3 9
6 6 8

a. Develop a Gantt chart to determine the total time required to process all six jobs. Use the following sequence of jobs: 1, 2, 3, 4, 5, 6

b. Can you develop a better sequence to reduce the total time required for processing?