Question: Slack time in IT projects represents: a . The time buffer added to the critical path to account for uncertainties. b . The amount of

Slack time in IT projects represents:
a. The time buffer added to the critical path to account for uncertainties.
b. The amount of time a task can be delayed without causing a delay to subsequent tasks.
c. The time allocated for non-essential tasks in a project.