Question: Slack time is equal to: the difference between an activity's latest and earliest expected completion time the latest expected completion time the sum of an

Slack time is equal to:
the difference between an activity's latest and earliest expected completion time
the latest expected completion time
the sum of an activity's latest and earliest expected completion time
the difference between the start time and realistic time for each activity
 Slack time is equal to: the difference between an activity's latest