Question: solve it please. 14. Using the basic chart below develop a Gantt chart showing the tasks, elapsed time, and completion day for the following project:
solve it please.
14. Using the basic chart below develop a Gantt chart showing the tasks, elapsed time, and completion day for the following project: to build a two car brick garage. A= 15 days Precedence None B= 10 days Precedence None C = 5 days Precedence A D= 3 days Precedence B E= 7 days Precedence D F=10 days Precedence E G= 5 days Precedence F 5 10 15 20 25 35 30 Task Completion Day: B D E F. G