Question: 40. Using the basic chart below develop a Gantt chart showing the tasks, elapsed time, and completion day for the following project: A= 10 days

40. Using the basic chart below develop a Gantt
40. Using the basic chart below develop a Gantt chart showing the tasks, elapsed time, and completion day for the following project: A= 10 days Precedence None B=5 days Precedence None C = 5 days Precedence A D= 10 days Precedence B E= 5 days Precedence D F=10 days Precedence E G= 5 days Precedence F Task 5 10 15 20 25 30 35 B D E F G G