Question: Solve the following graph for the minimum time to complete the project. The CPM graph with the links as shown in the table below Where
Solve the following graph for the minimum time to complete the project. The CPM graph with the links as shown in the table below Where the time cost in days for each link is: CPM Network Source Destination Cost (Days) A B 20 A C 6 A D 15 B E 12 C F 3 D E 5 E F 20 E G 16 F G 13 The minimum time to complete all activities from A to G is: