Question: A question for Critical Path Method (CPM) Calculation: Solve the following graph for the minimum time to complete the project. B (E A D G

A question for Critical Path Method (CPM) Calculation:

A question for Critical Path Method (CPM)

A question for Critical Path Method (CPM)

Solve the following graph for the minimum time to complete the project. B (E A D G F Where the time cost in days for each link is: CPM Network Source A Destination B D A Cost (Days) 17 9 17 7 A E B F. 8 D E 16 11 6 8 E F The minimum time to complete all activities from A to G is: a. None of the other choices O b. 49 O c. 52 O d. 25 O e. 30