Specifically, the following critical elements must be addressed. Use presentation notes (speaker notes) to articulate those points
Fantastic news! We've Found the answer you've been seeking!
Question:
Specifically, the following critical elements must be addressed. Use presentation notes ("speaker notes") to articulate those points that are not observable in the presentation:
- Demonstrate how EV, PV, and AC are used to calculate the following EVM measures: cost variance (CV), cost performance index (CPI), schedule variance (SV), schedule performance index (SPI),
- estimate to complete (ETC), estimate at completion (EAC), and variance at completion (VAC).
- Employ EVM equations to calculate the EVM measures (CV, SV, CPI, SPI) for the project in the case study.
- Explain the implications for the project in the case study when CPI is greater than or equal to 1.0, CPI is less than 1.0, SPI is greater than or equal to 1.0, and SPI is less than 1.0.
Related Book For
Discovering Advanced Algebra An Investigative Approach
ISBN: 978-1559539845
1st edition
Authors: Jerald Murdock, Ellen Kamischke, Eric Kamischke
Posted Date: