Question: Specifically, the following critical elements must be addressed. Use presentation notes (speaker notes) to articulate those points that are not observable in the presentation: Demonstrate

Specifically, the following critical elements must be addressed. Use presentation notes ("speaker notes") to articulate those points that are not observable in the presentation:


  1. Demonstrate how EV, PV, and AC are used to calculate the following EVM measures: cost variance (CV), cost performance index (CPI), schedule variance (SV), schedule performance index (SPI), 

  2. estimate to complete (ETC), estimate at completion (EAC), and variance at completion (VAC).
  3.  
  4. Employ EVM equations to calculate the EVM measures (CV, SV, CPI, SPI) for the project in the case study.
  5.  

  6. Explain the implications for the project in the case study when CPI is greater than or equal to 1.0, CPI is less than 1.0, SPI is greater than or equal to 1.0, and SPI is less than 1.0.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!