Question: Standard times: 2 . 0 min , 1 , 5 min, 3 . 0 min, 2 . 2 min You have the following additional information:
Standard times: min min, min, min You have the following additional information: Line efficiency is expected to be and transfer time between workstations is seconds repositioning time Find the following:
Required cycle time
Service time
Manning level
Work content time
Actual line efficiency
How many operators should be on each operation?
With that set up what will be the actual production of the line per day?