Question: step a = 7 minutes , Step B = 3 minutes, Step C 10 minutes, Step D = 6 minutes, Step E = 5 minutes

step a = 7 minutes , Step B = 3 minutes, Step C 10 minutes, Step D = 6 minutes, Step E = 5 minutes

If you could add one more resource to one of the steps (assuming each step is currently being done by an individual resource), what is the maximum hourly capacity you can achieve?