Question: Steve s machine shop has a machine which is designed to finish 3 cylinder heads per hour, and can run 2 4 hours a day.
Steves machine shop has a machine which is designed to
finish cylinder heads per hour, and can run hours a day.
To keep the machine in good shape, Steve shuts it down
times per day for half an hour each time to perform
maintenance.
Last week the shop is open days Steve machined
heads.
What is his Design capacity? Effective capacity? Utilization?
Efficiency?