Question: Subject: material management This is a subjective question, hence-you have to write your answer in the Text-Field given below. A bill of materials with lead

Subject: material management
This is a subjective question, hence-you have to write your answer in the Text-Field given below. A bill of materials with lead time (in weeks), on-hand quantities, lot sizes and scheduled receipts for product A are shown below. Numbers within () denotes number of corresponding items required for one parent item. a. Construct BOM tree with structure [1] b. For a requirement of 50 units, 100 units of A in week 5 and week 6 respectively prepare a MRP [5] Do not type the answer; write the answer by hand. Only hand-written material will be evaluated, Also, do not attach any file or screenshot or computer output of PPT/Excel/pdf, etc