Question: Subject : Project Management Project Example: Task Preceding Task Duration Task D Start 4 Weeks Task A Start 6 Weeks Task F D, A 7

Subject : Project Management

Project Example:

Task

Preceding Task

Duration

Task D

Start

4 Weeks

Task A

Start

6 Weeks

Task F

D, A

7 Weeks

Task E

D

8 Weeks

Task G

F, E

5 Weeks

Task B

F

5 Weeks

Task H

G

7 Weeks

Task C

H

8 Weeks

End

C, B

0 Weeks

1. How many possible paths are in this project?

2.What is the longest path (in weeks and then list the task names)

3.How long does it take to complete the project? (in weeks)

4.What is the slack of Task B? (In weeks)

5.What does the Float/Slack of Task B tell us?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!