Question: Subject : Project Management Project Example: Task Preceding Task Duration Task D Start 4 Weeks Task A Start 6 Weeks Task F D, A 7
Subject : Project Management
Project Example:
| Task | Preceding Task | Duration |
| Task D | Start | 4 Weeks |
| Task A | Start | 6 Weeks |
| Task F | D, A | 7 Weeks |
| Task E | D | 8 Weeks |
| Task G | F, E | 5 Weeks |
| Task B | F | 5 Weeks |
| Task H | G | 7 Weeks |
| Task C | H | 8 Weeks |
| End | C, B | 0 Weeks |
|
|
|
|
1. How many possible paths are in this project?
2.What is the longest path (in weeks and then list the task names)
3.How long does it take to complete the project? (in weeks)
4.What is the slack of Task B? (In weeks)
5.What does the Float/Slack of Task B tell us?