Question: Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks) Immediate
Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations:
| Activity | Duration (weeks) | Immediate Predecessor(s) |
|---|---|---|
| A | 21 | - |
| B | 12 | - |
| C | 14 | A |
| D | 6 | B |
| E | 4 | D |
| F | 13 | A,E |
| G | 3 | F |
| H | 7 | C,G |
What is the duration of the project? weeks?
What is the latest start week for activity B?
What is the slack time for activity G in weeks? If activity E were shortened by 3 weeks, what would be the new duration of the project in weeks?