Sun Oracle is launching a new computer component. The team has broken the project down into activities,
Fantastic news! We've Found the answer you've been seeking!
Question:
Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations:
Activity | Duration (weeks) | Immediate Predecessor(s) |
---|---|---|
A | 19 | - |
B | 9 | - |
C | 13 | A |
D | 7 | B |
E | 5 | D |
F | 11 | A,E |
G | 1 | F |
H | 6 | C,G |
What is the duration of the project?
weeks
What is the latest start week for activity C?
What is the slack time for activity E?
weeks
If activity D were shortened by 4 weeks, what would be the new duration of the project?
weeks
Related Book For
Intermediate Algebra
ISBN: 9780134895987
13th Edition
Authors: Margaret Lial, John Hornsby, Terry McGinnis
Posted Date: