Question: Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks) Immediate
Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations:
| Activity | Duration (weeks) | Immediate Predecessor(s) |
|---|---|---|
| A | 19 | - |
| B | 9 | - |
| C | 13 | A |
| D | 7 | B |
| E | 5 | D |
| F | 11 | A,E |
| G | 1 | F |
| H | 6 | C,G |
What is the duration of the project?
weeks
What is the latest start week for activity C?
What is the slack time for activity E?
weeks
If activity D were shortened by 4 weeks, what would be the new duration of the project?
weeks