Question: PM.53Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks) Immediate
PM.53Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations:
| Activity | Duration (weeks) | Immediate Predecessor(s) |
|---|---|---|
| A | 18 | - |
| B | 9 | - |
| C | 17 | A |
| D | 7 | B |
| E | 6 | D |
| F | 13 | A,E |
| G | 1 | F |
| H | 5 | C,G |
What is the duration of the project? weeks What is the lateststart week for activity B? What is the slack timefor activityE? weeks If activity E were shortened by 2weeks, what would be the newduration of the project? weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
