Question: Superb Manufacturing is using kanban system for a component part. The demand for the component is 223 parts/hr. A container with 32 parts can be
Superb Manufacturing is using kanban system for a component part. The demand for the component is 223 parts/hr. A container with 32 parts can be manufactured and delivered in 77 min. The safety factor is set to 8% of hourly demand.
What is demand during lead time?
Please include an explanation as well as the answer
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts