Question: Suppose that a project management team is trying to set up a realistic schedule for the data gathering and proposal phases of a project. The
Suppose that a project management team is trying to set up a realistic schedule for the data gathering and proposal phases of a project. The team looks over the situation and lists the activities that need to be accomplished along with the dependencies (as detailed below).
Suppose that a project management team is trying to set up a realistic schedule for the data gathering and proposal phases of a project. The team looks over the situation and lists the activities that need to be accomplished along with the dependencies (as detailed below).
| Activities | Immediate Predecessor | Expected Duration |
| A. Conduct Interviews | None | 3 Days |
| B. Administer Questionnaires | None | 4 Days |
| C. Read Company Reports | A, B | 4 Days |
| D. Analyze Data Flow | C | 7 Days |
| E. Introduce Prototype | C | 7 Days |
| F. Observe Reactions to Prototype | C | 7 Days |
| G. Perform Cost/Benefit Analysis | B, E | 6 Days |
| H. Prepare Proposal | F, G | 2 Days |
| I. Present Proposal | G, H | 1 Days |
| J. Rest | D, I | 3 Days |
Select ALL the tasks in the critical path(s)?
Group of answer choices
A
B
C
D
E
F
G
H
I
J
What is the latest possible completion time for activity G?
Group of answer choices
14
18
21
24
None of these choices