Question: Suppose that a project management team is trying to set up a realistic schedule for the data gathering and proposal phases of a project. The

Suppose that a project management team is trying to set up a realistic schedule for the data gathering and proposal phases of a project. The team looks over the situation and lists the activities that need to be accomplished along with the dependencies (as detailed below).

Suppose that a project management team is trying to set up a realistic schedule for the data gathering and proposal phases of a project. The team looks over the situation and lists the activities that need to be accomplished along with the dependencies (as detailed below).

Activities Immediate Predecessor Expected Duration
A. Conduct Interviews None 3 Days
B. Administer Questionnaires None 4 Days
C. Read Company Reports A, B 4 Days
D. Analyze Data Flow C 7 Days
E. Introduce Prototype C 7 Days
F. Observe Reactions to Prototype C 7 Days
G. Perform Cost/Benefit Analysis B, E 6 Days
H. Prepare Proposal F, G 2 Days
I. Present Proposal G, H 1 Days
J. Rest D, I 3 Days

Select ALL the tasks in the critical path(s)?

Group of answer choices

A

B

C

D

E

F

G

H

I

J

What is the latest possible completion time for activity G?

Group of answer choices

14

18

21

24

None of these choices

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!