Question: Suppose that a task in a project has the following time estimates: to=optimisticcompletiontime=5weekstm=mostlikelycompletiontime=15weekstp=pessimisticcompletiontime=18weeks Compute the expected task variance. The task expected task variance is weeks.

Suppose that a task in a project has the following time estimates: to=optimisticcompletiontime=5weekstm=mostlikelycompletiontime=15weekstp=pessimisticcompletiontime=18weeks Compute the expected task variance. The task expected task variance is weeks. (Enter your response rounded to two decimal places.)