Question: Suppose that a task in a project has the following time estimates: to= optimistic completion time =2 weeks tm= most likely completion time =17 weeks

Suppose that a task in a project has the following time estimates: to= optimistic completion time =2 weeks tm= most likely completion time =17 weeks tp= pessimistic completion time =19 weeks Compute the expected task variance. The task expected task variance is weeks. (Enter your response rounded to two decimal places.)