Question: Suppose that a task in a project has the following time estimates: to= optimistic completion time =2 weeks tm= most likely completion time =17 weeks

 Suppose that a task in a project has the following time

Suppose that a task in a project has the following time estimates: to= optimistic completion time =2 weeks tm= most likely completion time =17 weeks tp= pessimistic completion time =19 weeks Compute the expected task variance. The task expected task variance is weeks. (Enter your response rounded to two decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!