Question: Suppose that a task in a project has the following time estimates: t o = optimistic completion time = 2 weeks t m = most

Suppose that a task in a project has the following time estimates:
to= optimistic completion time =2 weeks
tm= most likely completion time =12 weeks
tp= pessimistic completion time =18 weeks
Compute the expected task variance.
The task expected task variance is weeks. (Enter your response rounded to two decimal places.)