Question: Suppose that the normal time for activity C is 10 weeks with a normal cost of $6,000. We can crash it to only 4 weeks
Suppose that the normal time for activity C is 10 weeks with a normal cost of $6,000. We can crash it to only 4 weeks at a total cost of $12,000. The total activity cost if we crash it to 7 weeks will be A. $9,000. B. $8,000. C. $11,000. D. $6,000