Question: Suppose that you are assigned to a construction project which is planned to be build as early as possible. As a planning engineer you have
Suppose that you are assigned to a construction project which is planned to be build as early as possible. As a planning engineer you have to find the right sequence of activities in order to complete the project on time. Use Gantt (Bar) Chart and calculate total duration and determine the critical path of the project.
Immediate Predecessor (Finish to Start)
a) Construct Gantt Chart of the project.
b) Identify the critical path. (hint: look for the longest path)
Soose that you are assigned to a construction project which is planned to be build as early as possible. As a planning engineer you have to find the right sequence of activiti order to complete the project on time. Use GanttiBan Chart and calculate total duration and determine the critical path of the project Activity Immediate Predecessors Estimated Duration C D Activity Description Excavate Lay the foundation Put up the rough wall Put up the rool Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting Do the electrical work Put up the wallboard Install the flooring Do the interior painting Install the exterior fixtures Install the interior fixtures H 2 weeks 4 weeks 10 weeks 6 weeks 4 weeks 5 weeks 7 weeks 9 weeks 7 weeks 8 weeks 4 weeks 5 weeks 2 weeks 6 weeks 1 N M KL immediate Predecessor Finish to Start) Construct Gantt Chat of the project Identify the critical path Chint look for the longest pathStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
