Question: Suppose that you are assigned to a construction project which is planned to be build as early as possible. As a planning engineer you have

Suppose that you are assigned to a construction project which is planned to be build as early as possible. As a planning engineer you have to find the right sequence of activities in order to complete the project on time. Use Gantt (Bar) Chart and calculate total duration and determine the critical path of the project. Suppose that you are assigned to a construction

Immediate Predecessor (Finish to Start)

a) Construct Gantt Chart of the project.

b) Identify the critical path. (hint: look for the longest path)

Immediate Predecessors Activity UWODZ Activity Description Excavate Lay the foundation Put up the rough wall Put up the roof Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting Do the electrical work Put up the wallboard Install the flooring Do the interior painting Install the exterior fixtures Install the interior fixtures B E D EG F, 1 1 1 H KL Estimated Duration 2 weeks 4 weeks 10 weeks 6 weeks 4 weeks 5 weeks 7 weeks 9 weeks 7 weeks 8 weeks 4 weeks 5 weeks 2 weeks 6 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!