Question: Suppose you are the project manager for the project ALPHA. The following diagram shows the overall status of the project. Based on the diagram, is

Suppose you are the project manager for the

Suppose you are the project manager for the project ALPHA. The following diagram shows the overall status of the project. Based on the diagram, is the project status/condition good or bad? Give your explanation by using schedule performance index and cost performance index. 1.6 1.4 1.2 1.0 0.8 0.6 under budget ahead of schedule over budget behind schedule S 0.4 8 9 1 2 3 4 5 6 7 Project Week