Question: Suppose you have a three task sequence. All customers go to Task A. After task A, 60% of customers go to Task B; the other
Suppose you have a three task sequence. All customers go to Task A. After task A, 60% of customers go to Task B; the other 40% go to task C. After task B or C, all customers then go to Task D before leaving. No buffers exist between tasks, so blocking/starvation rules apply.
Suppose throughput capacities are as follows. Task A: 10 customers/hour; task B: 5 customers/hour; task C: 6 customers/hour; task D, 12 customers/hour.
Use this information to answer the next 3 questions.
At what rate will customers leave task D (in customers/hour)? Pick the closest answer.
Group of answer choices
1
3
5
7
9
11
Question 491
The utilization of Task B is closest to which of the following?
Group of answer choices
0%
20%
40%
60%
80%
100%
Question 501
What is the bottleneck in the A-C-D process route?
Group of answer choices
A
B
C
D