Question: Susan is scheduling two activities: Write draft and Edit draft. She can start Edit draft when completing Write draft. Instead of waiting until Write draft
Susan is scheduling two activities: "Write draft" and "Edit draft". She can start "Edit draft" when completing "Write draft". Instead of waiting until "Write draft" is fully completed, she should start "Edit draft" two days before fully completing "Write draft". Which one best describes the precedence relationship between the two activities?
Group of answer choices
starttofinish SF with day lag
starttofinish SF with day lead
finishtostart FS with day lead
finishtostart FS with day lag
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock