Question: Susan is scheduling two activities: Write draft and Edit draft. She can start Edit draft when completing Write draft. Instead of waiting until Write draft

Susan is scheduling two activities: "Write draft" and "Edit draft". She can start "Edit draft" when completing "Write draft". Instead of waiting until "Write draft" is fully completed, she should start "Edit draft" two days before fully completing "Write draft". Which one best describes the precedence relationship between the two activities?
Group of answer choices
start-to-finish (SF) with 2-day lag
start-to-finish (SF) with 2-day lead
finish-to-start (FS) with 2-day lead
finish-to-start (FS) with 2-day lag