tab Problem #2 Crashing - has the information for the project. Answer questions A to F...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
tab "Problem #2 Crashing" - has the information for the project. Answer questions "A" to "F" by completing The the tables (make sure to scroll down to find parts: D, E and F. Assume an indirect cost of $300/day. Complete the tables and write up your narrative in the text box provided. Activity A B C D Path E F G H Predecessor Normal Time B A, C A, C B D E, F Crash Crash Cost Direct Cost Indirect Cost Total Cost Duration (Normal Time) 5 4 7 2 3 8 5 6 Normal Cost $500 $400 $700 $200 $300 $800 $500 $600 Crash Time Crash Cost 3 2 6 1 - 5 4 3 $1,500 $2,000 $1,600 $500 $2,900 $1,000 $1,800 Part D: The Plan for 18 days (complete the table below - there maybe more columns/rows than needed] Crash cost/day ? ? ? ? ? ? ? ? Part C Max Crash Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Note: You don't need to submit the network diagram, but it is strongly recommended the you make a network diagram that you will use as you decide how many paths you have, their length, and then use the network as you crash activities. ? ? (A) List the critical activities (B) Completion time (normal time): (C) calculate crash cost per day (D), (E), and (F) Complete the tables (scroll down to see all of them). Write your answer in the text boxes provided. Part D: To get to 18 days, explain what you crashed (in order of crashing) and the total cost of the plan. Part E: The Plan for 16 days (complete the table below - there maybe more columns/rows than needed) Path Duration (Normal Time) Crash Crash Cost Direct Cost Indirect Cost Total Cost Path Part F: The Plan for the shortest possible time for this project (complete the table below - there maybe more columns/rows than needed) Duration (Normal Time) Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Crashi Crash Cost Direct Cost Indirect Cost Total Cost Iteration 1 Part E: To get to 16 days, explain what you crashed (in order of crashing) and the total cost of the plan. Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Part F: What is the shortest time to complete this project, how did you get to this timing (provide what was crashed and the order) and what is the total cost for this plan? tab "Problem #2 Crashing" - has the information for the project. Answer questions "A" to "F" by completing The the tables (make sure to scroll down to find parts: D, E and F. Assume an indirect cost of $300/day. Complete the tables and write up your narrative in the text box provided. Activity A B C D Path E F G H Predecessor Normal Time B A, C A, C B D E, F Crash Crash Cost Direct Cost Indirect Cost Total Cost Duration (Normal Time) 5 4 7 2 3 8 5 6 Normal Cost $500 $400 $700 $200 $300 $800 $500 $600 Crash Time Crash Cost 3 2 6 1 - 5 4 3 $1,500 $2,000 $1,600 $500 $2,900 $1,000 $1,800 Part D: The Plan for 18 days (complete the table below - there maybe more columns/rows than needed] Crash cost/day ? ? ? ? ? ? ? ? Part C Max Crash Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Note: You don't need to submit the network diagram, but it is strongly recommended the you make a network diagram that you will use as you decide how many paths you have, their length, and then use the network as you crash activities. ? ? (A) List the critical activities (B) Completion time (normal time): (C) calculate crash cost per day (D), (E), and (F) Complete the tables (scroll down to see all of them). Write your answer in the text boxes provided. Part D: To get to 18 days, explain what you crashed (in order of crashing) and the total cost of the plan. Part E: The Plan for 16 days (complete the table below - there maybe more columns/rows than needed) Path Duration (Normal Time) Crash Crash Cost Direct Cost Indirect Cost Total Cost Path Part F: The Plan for the shortest possible time for this project (complete the table below - there maybe more columns/rows than needed) Duration (Normal Time) Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Crashi Crash Cost Direct Cost Indirect Cost Total Cost Iteration 1 Part E: To get to 16 days, explain what you crashed (in order of crashing) and the total cost of the plan. Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Part F: What is the shortest time to complete this project, how did you get to this timing (provide what was crashed and the order) and what is the total cost for this plan?
Expert Answer:
Related Book For
Income Tax Fundamentals 2013
ISBN: 9781285586618
31st Edition
Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill
Posted Date:
Students also viewed these accounting questions
-
Study the following reaction scheme: a. Identify the substances A to F by giving their names and formulae. b. Write a balanced chemical equation for the formation of gas B. c. (i) Describe a chemical...
-
Complete Table 5.1 to find each Box effect by calculating the Box average (Brand effect + grand mean). Crossed effects always sum to zero. Nested effects (Box) also sum to zero within each...
-
Scroll down to complete all parts of this task. Select from the option list provided the correct accounting treatment of gains and losses when the investment securities are reclassified. Each choice...
-
EarthTones, Inc., was a wholly owned subsidiary of Cutlinger Corporation. Several years ago, EarthTones acquired numerous oil leases and began exploration activities to determine their suitability...
-
Five couples are having dinner at a fancy French restaurant. They expect that the total dinner bill will be split evenly five ways. How might this prior knowledge affect the diners menu selections?...
-
Most televised baseball games display a pitch tracker that shows whether the pitch was in the strike zone, which in turn shows whether the umpire made the correct call. Major League Baseball keeps...
-
State a conclusion. Exercises 49 refer to the following data: Electric motors are assembled on four different production lines. Random samples of motors are taken from each line and inspected. The...
-
Research suggests that liberals and conservatives respond differently to gaze cuing, which is the tendency to shift attention in the direction suggested by another person's eye movements (Dodd,...
-
Begin by locating an article within the last few years related to leading by example (.org or .edu) . After you have read the article, give a response to each of these statements: Summarize the...
-
Accenture recently published an article titled Meet the Finance 2020 Workforce, 18 suggesting that accountants will need to not only embrace traditional financial questions of What happened? and Why...
-
(a) Use the continuity and normalization conditions to evaluate the coefficients A and C in the deuteron wave functions. (b) From the resulting wave function, evaluate the root-mean-square radius of...
-
Configure a work breakdown structure (WBS) based on scope and plan.
-
Explain the way that eigenfaces are used in face recognition systems.
-
Outline the project planning process based on identified resources.
-
Explain how crossover, mutation, and reproduction affect schemata.
-
Describe how to strategically select, prioritize, and resource projects.
-
A major flaw in the policy analysis process is the lack of feedback. True/ false Working toward public support of a proposed health care policy is undertaken in the stage of the implementation...
-
Compare and contrast licensing and subcontracting.
-
Bev and Ken Hair have been married for 3 years. They live at 3567 River Street, Springfield, MO 63126. Ken is a full-time student at Southwest Missouri State University (SMSU) and Bev works as an...
-
David and Darlene Jasper have one child, Sam, who is 6 years old. The Jaspers reside at 4639 Honeysuckle Lane, Los Angeles, CA 90248. David's Social Security number is 577-11-3311, Darlene's is...
-
Quince Corporation has taxable income of $450,000 for its 2012 calendar tax year. Calculate the corporation's income tax liability for 2012 before tax credits. $_________
-
Typical accounting specialists with designations include all of the following except: a. Certified Financial Analyst (CFA) b. Certified Public Accountant (CPA) c. Certified Bookkeeper (CB) d....
-
The Financial Accounting Standards Board is the: a. Governmental group that sets financial accounting principles. b. International group that identifies preferred international accounting principles....
-
Generally accepted accounting principles do not aim to make information in financial statements: a. Reasonable b. Relevant c. Reliable d. Comparable
Study smarter with the SolutionInn App