Question: Table 1 1 - 2 The following represents a project with four activities. All times are in weeks. Most Pessimistic Activity Immediate Optimistic Predecessor Time
Table The following represents a project with four activities. All times are in weeks. Most Pessimistic Activity Immediate Optimistic Predecessor Time Likely Time Time A CA D B According to the data in Table what is the critical path? C D BCD A B
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
