Question: Table 1 1 - 2 The following represents a project with four activities. All times are in weeks. Most Pessimistic Activity Immediate Optimistic Predecessor Time

Table 11-2 The following represents a project with four activities. All times are in weeks. Most Pessimistic Activity Immediate Optimistic Predecessor Time Likely Time Time A2814888 CA6918 D B 51117 According to the data in Table 11-2, what is the critical path? C -D - B-C-D A -B