Question: 2. The following represents a project with four activities. All times are in weeks. Activity Most Immediate Optimistic Pessimistic Likely Predecessor Time Time Time 28

2. The following represents a project with four

2. The following represents a project with four activities. All times are in weeks. Activity Most Immediate Optimistic Pessimistic Likely Predecessor Time Time Time 28 - 8 8 8 A 6 9 18 B 5 11 17 B 14 C D The critical path is BID. The expected completion time is 19 days. Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. What is the probability that the project is finished in 22 weeks or more? (Round to two decimals.)