Question: Table 1 1. Use the information in partially completed Table 1. What is the projected on-hand inventory in week 5? A) 0 units B) 35

Table 1

Table 1 1. Use the information in partially completed Table 1. What 1. Use the information in partially completed Table 1. What is the projected on-hand inventory in week 5? A) 0 units B) 35 units C) 40 units D) 75 units

2. Use the information in partially completed Table 1. What is the MPS start quantity in week 2? A) 0 units B) 20 units C) 40 units D) 80 units

3. Use the information in partially completed Table 1. What is the available-to-promise (ATP) inventory in week 5? A) 0 units B) 35 units C) 53 units D) 80 units

4. Which one of the following is an input to the MRP system? A) shop-floor schedules B) financial reports C) master production schedule D) purchasing orders

Master Production Schedule: The following table shows the MPS start quantities for the next 10 weeks. Table 2

Finished Item A 1 2 3 4 5 6 7 8 9 10
MPS Start 20 40 30 20 40

Bill of Material: - Finished Goods A uses 2 each of component B, 1 each of component C. - Subassembly B uses 2 each of component D.

Selected Inventory Data: Table 3

Item Lot Sizing Rule Lead Time Scheduled Receipts On-Hand
B L4L 1 40 in period 1
C FOQ = 50 2 40
D POQ = 3 1 100

Construct the MRP schedule using the preceding information and answer the following questions.

is the projected on-hand inventory in week 5? A) 0 units B)

35 units C) 40 units D) 75 units 2. Use the information

in partially completed Table 1. What is the MPS start quantity in

5. Use the information above. How many units of B are needed to produce 10 units of A? A) 10 units B) 20 units C) 30 units D) 40 units

6. Use the information above. What is the projected on-hand inventory for B in week 5? A) 0 units B) 35 units C) 40 units D) 75 units

7. Use the information above. How many planned order releases are there for item B? A) zero or one B) two C) three D) more than three

8. Use the information above. What is the projected on-hand inventory for C in week 6? A) 0 units B) 30 units C) 40 units D) 75 units

9. Use the information above. What is the gross requirement for D in week 2? A) 0 units B) 80 units C) 160 units D) 240 units

10. Use the information above. What is the projected on-hand inventory for D in week 5? A) 0 units B) 35 units C) 120 units D) 160 units

12. Which of the following statements concerning MRP systems (MRP I and MRP II) of the 1970s/80s is inaccurate? A) MRP systems are driven by a MPS and show the quantity and timing of end-item production B) Initial MRP-focused on material only, produced a schedule of shop order manufacturing dates (and purchase order release dates) C) MRP II scope was expanded to address machine and labor resources D) MRPII could optimize the profit and on-time performance subject to constraints

13. In many organizations, information flows much more freely within functions than it does across functions. __________ represents an expanded effort to overcome this tendency. A) MRP B) ERP C) CRP D) MRPII

Order Policy: 80 units Lead Time: 1 week: Item: B Lot Size: L4L Lead Time: 1 week Item: C Lot Size: FOQ=50 Lead Time: 2 weeks Item: D Lot Size: POQ=3 Lead Time: 1 week

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!