Question: Table 1 8 . 2 3 Job A B C D E Processing time ( weeks ) 2 0 . 5 1 3 1 .

Table 18.23
Job A B C D E
Processing time (weeks)20.5131.5
Due Date (Weeks)36452
Question at position 7
7
4 points
Question at position 7
If the jobs displayed in table 18.23 are processed using the earliest-due-date rule, what would be...
Prompt 112. The lateness of Job B?
Answer for prompt 112. The lateness of Job B?
Prompt 213. The tardiness of Job E?
Answer for prompt 213. The tardiness of Job E?
Prompt 314. The Maximum tardiness?
Answer for prompt 314. The Maximum tardiness?
Prompt 415. Average flow time?