Question: Table 1 8 . 2 2 Job A B C D E Processing Time ( minutes ) 1 4 2 3 5 Weight 1 .
Table
Job A B C D E
Processing Time minutes
Weight
Question at position
point
Question at position
Assume the jobs displayed in Table need to be processed on a single resource and are sequenced with the WSPT rule. Which job would be processed second?