Question: Table 11-5 Activity Immediate Predecessor Time A -- 6 B -- 4 C A 5 D B 5 E D 4 F C, D 3

Table 11-5 Activity Immediate Predecessor Time A -- 6 B -- 4 C A 5 D B 5 E D 4 F C, D 3 G E, F 8 H E 2 Using the data in Table 11-5, determine the latest time activity E can be finished and not delay the completion of the project? 13 10 9 14