Question: Table 7 . 1 3 All activity times for the project are in weeks. table [ [ Activity , Predecessor,Optimistic,Most Likely,Pessimistic ] , [
Table
All activity times for the project are in weeks.
tableActivityPredecessor,Optimistic,Most Likely,PessimisticABCDAECFBGFHD E G
Using Table what is the critical path of this project?
CEH
CEH and BFGH are both critical.
ADH
BFGH
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
