Question: Table 7 . 1 3 All activity times for the project are in weeks. table [ [ Activity , Predecessor,Optimistic,Most Likely,Pessimistic ] , [

Table 7.13
All activity times for the project are in weeks.
\table[[Activity,Predecessor,Optimistic,Most Likely,Pessimistic],[A,--,12,16,25],[B,--,7,14,22],[C,--,5,10,14],[D,A,15,18,25],[E,C,8,12,18],[F,B,9,12,15],[G,F,18,22,29],[H,D, E, G,15,19,27]]
Using Table 7.13, what is the critical path of this project?
C-E-H
C-E-H and B-F-G-H are both critical.
A-D-H
B-F-G-H
 Table 7.13 All activity times for the project are in weeks.