Question: Table 7 . 1 3 All activity times for the project are in weeks. table [ [ Activity , Predecessor,Optimistic,Most Likely,Pessimistic ] , [

Table 7.13
All activity times for the project are in weeks.
\table[[Activity,Predecessor,Optimistic,Most Likely,Pessimistic],[A,cdots,12,16,25],[B,cdots,7,14,22],[C,cdots,5,10,14],[D,A,15,18,25],[E,C,8,12,18],[F,B,9,12,15],[G,F,18,22,29],[H,D,E,G,15,19,27],[,,,,]]
Using Table 7,13, what is the critical path of this project?
B-F-G-H
O C-E-H and B-F-G-H are both critical.