Question: A project comprises the activities shown in the Table below, which also shows the duration of each activity. Table 2: Activities and duration of project
A project comprises the activities shown in the Table below, which also shows the duration of each activity.
Table 2: Activities and duration of project
|
|
|
| Duration in weeks | |
| Activity | Preceding activity | Optimistic | Most likely | Pessimistic |
| A | - | 2 | 3 | 3 |
| B | - | 10 | 12 | 15 |
| C | A | 4 | 5 | 8 |
| D | B | 2 | 2 | 2 |
| E | A,D | 3 | 3 | 3 |
| F | B | 3 | 4 | 5 |
| G | C,E,F | 8 | 10 | 20 |
| H | G | 2 | 3 | 5 |
| I | G | 2 | 2 | 2 |
| J | H | 4 | 5 | 10 |
| K | I,J | 2 | 4 | 6 |
Construct a network diagram for this project.
Calculate the expected completion tine and variance of all activities.
Determine ES, LS, EF, and LF for each activity.
Calculate the slacks.
Determine the critical paths and all critical activities.
Determine the probability that the project will take less than 42 weeks.