Question: Table 7 . 4 table [ [ Activity , Predecessor,Time ( weeks ) ] , [ A , - - , 6 ] ,

Table 7.4
\table[[Activity,Predecessor,Time(weeks)],[A,--,6],[B,--,6],[C,A,4],[D,B,9],[E,C,D,11],[F,E,3]]
Using Table 7.4, what is the largest amount of slack that any activity in the project has? two weeks
three weeks
zero weeks
four weeks
 Table 7.4 \table[[Activity,Predecessor,Time(weeks)],[A,--,6],[B,--,6],[C,A,4],[D,B,9],[E,C,D,11],[F,E,3]] Using Table 7.4, what is the largest amount