Question: Table 7 . 4 table [ [ Activity , Predecessor,Time ( weeks ) ] , [ A , - - , 6 ] ,
Table
tableActivityPredecessor,TimeweeksABCADBECDFE
Using Table what is the largest amount of slack that any activity in the project has? two weeks
three weeks
zero weeks
four weeks