Question: Table 7 . 5 table [ [ Activity , Predecessor,Time ( days ) ] , [ A , - - , 8 ] ,

Table 7.5
\table[[Activity,Predecessor,Time (days)],[A,--,8],[B,--,6],[C,--,3],[D,A,B,10],[E,C,8],[F,A,5],[G,D,E,3],[H,G,4]]
Using Table 7.5, what is the earliest that activity D can be finished?
18 days
25 days
13 days
8 days
 Table 7.5 \table[[Activity,Predecessor,Time (days)],[A,--,8],[B,--,6],[C,--,3],[D,A,B,10],[E,C,8],[F,A,5],[G,D,E,3],[H,G,4]] Using Table 7.5, what is the earliest