Question: Table 7.4 Activity Predecessor Time(weeks) A -- 6 B -- 6 C A 4 D B 9 E C,D 11 F E 3 Using Table
Table 7.4
| Activity | Predecessor | Time(weeks) |
| A | -- | 6 |
| B | -- | 6 |
| C | A | 4 |
| D | B | 9 |
| E | C,D | 11 |
| F | E | 3 |
Using Table 7.4, what is the earliest completion time for this project?
Group of answer choices
18 weeks
22 weeks
25 weeks
20 weeks