Question: Table 7.4 Activity Predecessor Time(weeks) A -- 6 B -- 6 C A 4 D B 9 E C,D 11 F E 3 Using Table

Table 7.4

Activity Predecessor Time(weeks)
A -- 6
B -- 6
C A 4
D B 9
E C,D 11
F E 3

Using Table 7.4, what is the earliest completion time for this project?

Group of answer choices

18 weeks

22 weeks

25 weeks

20 weeks